Workshop setup and industrial machine installation
Taqnia Technical Services delivered the Yamama Project for YAMAMA Cement Company to establish a fully equipped workshop and install the required industrial machines for maintenance activities.
Client
YAMAMA Cement Company
Location
Saudi Arabia
Project Overview
Taqnia Technical Services delivered the Yamama Project for YAMAMA Cement Company to establish a fully equipped workshop and install the required industrial machines for maintenance activities. The project covered machine unloading, positioning, installation, leveling, electrical and utility connections, testing, commissioning, operator training, preventive maintenance training, and final handover to ensure the workshop was ready for safe and practical day-to-day use.
Client Objective
The client required a workshop that was properly set up, fully equipped, and operational to support internal maintenance activities. The main objectives were to establish a complete workshop environment, install the machines correctly, train operators, and hand over the workshop in a ready-to-use condition with stable machine performance.
Gallery
Workshop photos
Installation & commissioning highlights




Equipment Included
- Heavy Duty Lathe Machine
- Conventional Lathe Machine
- Plate Rolling Machine
- Hydraulic Press Brake
- Guillotine Shearing Machine
- Universal Milling Machine
- Surface Grinding Machine
- Horizontal Bandsaw Machine
- Slotting Machine
- Radial Drilling Machine
- Sand Blasting Machine
- Abrasive Cut-Off Saw Machine
- MIG Welding Machine
- Air Compressor Dryer Unit
Delivery plan
Scope of Work
- Machine unloading and positioning
- Installation and leveling of workshop machines
- Electrical connection works
- Utility hook-up and commissioning support
- Testing and commissioning
- Operator training and preventive maintenance training
- Final handover
Challenges During Execution
The project required careful coordination of site preparation, machine handling, utility connections, installation sequence, commissioning activities, operator training readiness, and overall timing. These factors demanded disciplined execution to ensure that the workshop was completed in an organized and reliable manner.
Implementation Approach
The work was executed in a structured sequence beginning with machine unloading, positioning, and leveling in accordance with the workshop layout. Electrical and utility hook-ups were completed, followed by systematic testing and commissioning for each machine. Operator training and preventive maintenance training were then conducted to support safe operation and long-term workshop readiness before final handover.
Results
- Fully operational workshop achieved
- Successful project handover completed
- Operators trained for safe and effective machine use
- Workshop ready to support maintenance work
- Stable machine performance after testing and commissioning
Value Delivered
This project demonstrated Taqnia Technical Services' ability to deliver complete workshop setup solutions that combine machine installation, commissioning, operator training, and maintenance readiness. The delivered value included operational workshop readiness, improved in-house maintenance capability, trained personnel, smooth project coordination, and stable machine performance after handover.
Executive Summary
The Yamama Project for YAMAMA Cement Company was successfully completed by Taqnia Technical Services through workshop setup and machine installation works supported by testing, commissioning, training, and maintenance preparation. Despite the coordination demands of site preparation, handling, utilities, sequencing, and training readiness, the project was executed successfully and handed over as a fully operational workshop ready for maintenance work.